With limited time and incomplete input, the project presented unique challenges. Oriole meticulously modeled all elements based on the provided documents and applied logical assumptions where necessary. Any unclear information or identified issues were submitted for review, ensuring accuracy and alignment with project requirements. Through strategic problem-solving and efficient execution, Oriole successfully delivered a well-coordinated model.About Project:
This project involved a two-story school building where Oriole Design Tech Solutions was responsible for 3D modeling of architectural, structural, and plumbing elements. The model was created to facilitate coordination with other trades and to identify any gray areas in the input documents.
Building Type:
School in Utah
Project Area:
93,186 sq. ft.
Trades Covered:
Scope of Work:
Level of Development:
LOD 300
Project Timeline:
1 Weeks
Resources Used:
1 Engineers
RFI Raised:
We have raised around 14 RFIs for missing information, constructability issues, etc.
Software Used: