However, discrepancies in the 2D drawings, missing information, and a lack of actual site data led to repeated revisions. These challenges necessitated in-person site audits to verify installations and ensure alignment between the model and real-world conditions. Through careful coordination and validation, Oriole helped streamline the process and enhance project accuracy.About Project:
Oriole Design Tech Solutions was responsible for 3D LOD 350 modeling of architectural, structural, and MEPF elements, including the MEPFP shop drawings. The objective was to create an accurate, clash-free model and shop drawings to support seamless project execution.
Building Type:
Hospital Building
Project Area:
Trades Covered:
Scope of Work:
Level of Development:
LOD 350
Project Timeline:
24 Weeks
Resources Used:
8 Architects & Engineers
RFI Raised:
We have raised around 146 RFIs for missing information, constructability issues, etc.
Software Used: