Given the involvement of multiple critical trades and specialized hospital services, effective coordination between these trades and timely drawing updates presented a significant challenge. Oriole’s team worked diligently to ensure seamless integration and resolved conflicts promptly, ensuring that all systems were accurately represented and aligned. This careful coordination was essential in meeting the complex requirements of the hospital facility, ensuring efficient design and construction.About Project:
Oriole Design Tech Solutions provided 3D modeling, and coordination services along with prepared shop and prefab drawings for plumbing, electrical, and mechanical systems.
Building Type:
Hospital (Replacement)
Project Area:
Trades Covered:
Scope of Work:
Level of Development:
LOD 400
Project Timeline:
18 Weeks
Resources Used:
3 Architects & Engineers
RFI Raised:
We have raised around 36 RFIs for missing information, constructability issues, etc.
Software Used: