As this was an amusement facility, so the building was not in a regular shape. Moreover, due to the involvement of multiple trades and multiple changes involved coordination was a real challenge for this project. We have reviewed each changes and issues precisely and in case of any mismatch or conflict we have raised many RFIs with intelligent and logical solution.About Project:
Oriole Design Tech Solutions was responsible for 3D model, shop drawing and prefabrication drawing preparation of plumbing. Clash coordination with other services.
Building Type:
Amusement Park
Project Area:
Trades Covered:
Scope of Work:
Level of Development:
LOD 350
Project Timeline:
22 Weeks
Resources Used:
5 Engineers
RFI Raised:
We have raised around 39 RFIs for missing information, constructability issues, etc.
Software Used: